CHAPTER 5. IN-ROOM TERMINAL SYSTEMS

Very early in the design process, the HVAC design engineer must analyze and ultimately select appropriate systems, as discussed in Chapter 1. Next, production of heating and cooling is selected as decentralized (see Chapter 2) or centralized (see Chapter 3). Finally, distribution of heating and cooling to the end-use space can be done by an all-air system (see Chapter 4), or a variety of all-water or air/water systems and local terminals, as discussed in this chapter.

One option is using in-room terminal systems to provide heating and/or cooling to individual zones. Terminal units include consoles, fan-coils, blower coils, unit ventilators, chilled beams, and radiant panels. Terminal systems add heat energy or absorb the heat in the conditioned space served. The medium that transfers the heat either from the space to the outdoors or from a heat source to the conditioned spaces may be the same as used with nonterminal systems. Typical uses of in-room terminal unit systems include hotels/motels, apartments and multifamily dwellings, classrooms, and health care facilities. In older office buildings, in-room terminal units were commonly used for perimeter rooms, combined with central air handlers that served the interior spaces. Systems of this type are making a comeback with the introduction of variable-refrigerant-flow (VRF) equipment, combined with dedicated outdoor air systems (DOAS). Historical preservation projects often use in-room terminal units to minimize the space problems due to running ductwork in historical structures.

1. SYSTEM CHARACTERISTICS

Terminal-unit systems can be designed to provide complete sensible and latent cooling and heating to an end-use space; however, most terminal systems are best used with a central ventilation system providing pretreated air to the space. Heat can be provided by hot water, steam, or an electric heating coil. Cooling can be provided by chilled-water or direct-expansion (DX) coils. Heat pumps (discussed in Chapter 2) can be used, either with a piped water loop (water-source) or air cooled. In-room terminals usually condition a single space, but some (e.g., a large fan-coil unit) may serve several spaces. In-room terminal systems can allow individual space control of heating or cooling during intermediate seasons; satisfying the heating and cooling needs of various rooms on a single system. A thermostat for each terminal unit provides individual zone temperature control.

A terminal unit used with central ventilation provides the cooling or heating necessary to handle only the sensible heat gain or loss caused by the building envelope and occupancy. Ventilation, or primary, air is delivered by a separate ducted system, either to the terminal unit or ducted directly to the space, and should be pretreated to handle the total latent load of the ventilation air, occupancy, and the space, as well as the sensible load of the ventilation air.

Terminal units without central ventilation require additional coil capacity to heat or cool and dehumidify the ventilation air required for the end space. Terminal units are commonly small, with minimal coil rows; therefore, providing this additional capacity is often difficult. Care must be taken to minimize the risk of frozen coils in the winter, and to have enough cooling capacity to not only cool, but also dehumidify ventilation air in the summer. Terminal units have very small fans, so ventilation air must be provided to the unit from a central fan-powered source or supplied from a nearby opening in the building skin, thereby limiting the location of terminal units to the exterior wall of the building.

Although a single in-room terminal unit can be applied to a single room of a large building, this chapter covers applying multiple in-room terminal units to form a complete air-conditioning system for a building.

 Advantages

Advantages of all in-room terminal unit systems include the following:

  • The delivery system for the space heating and cooling needs (piping versus duct systems) requires less building space (a smaller central fan room, or none, and little duct space)

  • System has all the benefits of a central water chilling and heating plant, but allows local terminals to be shut off in unused areas

  • Individual room temperature control allows each thermostat to be adjusted for a different temperature

  • Minimal cross contamination of recirculated air

  • Because this system can heat with low-temperature water, it is particularly suitable for use with solar or low-temperature/high-efficiency boilers or with heat recovery equipment

  • Failure of a single in-room unit affects only the one room, allowing other spaces to continue to operate

  • Facilities personnel can remove and replace an in-room terminal unit in hours, allowing them to install a spare and have the room back in service quickly; units are comparatively inexpensive, small, and light, so the owner has the option of stocking spare units on the premises

  • Maintenance procedures generally can be done by nonlicensed HVAC personnel, allowing in-house crews to complete the tasks

  • Controls for each unit are very simple

  • Central control systems can be incorporated to control unit operation and space temperatures during unoccupied hours

In-room terminal unit systems with central ventilation air have these additional advantages:

  • The central air-handling apparatus used for central ventilation air is smaller than that of an all-air system because less air must be conditioned at that location.

  • Space can be heated without operating the primary air system, using just the in-room terminal units. Nighttime primary fan operation is avoided in an unoccupied building. Emergency power for heating, if required, is much lower than for most all-air systems.

  • Dehumidification, filtration, and humidification of ventilation air are performed in a central location remote from conditioned spaces.

  • They allow using central heat recovery devices such as heat wheels.

  • Ventilation air is positively supplied and can accommodate constant recommended outdoor air quantities, regardless of the temperature control of the room.

  • Use of central ventilation air with terminal units in some climates can prevent the negative pressurization problems that occur when occupants turn off in-room units.

 Disadvantages

  • For many buildings, in-room terminals are limited to perimeter space; separate systems are required for other areas.

  • In-room terminal unit fans with very little if any ductwork can be noisy. Many manufacturers have addressed this and provided units that are acceptable in many situations.

  • Because of the individual space control, more controls are needed than for many all-air systems.

  • The system is not appropriate for spaces with high exhaust requirements (e.g., research laboratories) unless supplementary ventilation air is provided.

  • Central dehumidification eliminates condensation on the secondary-water heat transfer surface (see the section on Secondary-Water Distribution) under maximum design latent load, but abnormal moisture sources (e.g., open windows, cooking, people congregating, a failed primary-air system) can cause annoying or damaging condensation. Therefore, a condensate pan must be provided as for other systems.

  • Primary-air supply usually is constant with no provision for shut-off. This is a disadvantage in residential applications, where tenants or hotel room guests may prefer to turn off the air conditioning, or where management may desire to do so to reduce operating expense; however, this can help to stabilize pressurization of a building when exhaust fans are centrally controlled or in constant operation.

  • Low chilled-water temperature and/or deep chilled-water coils are needed at the central ventilation air unit to control space humidity adequately. Low chilled-water temperatures can result in excessive condensation occurring at terminal units, if chilled-water valves are not used to shut off water flow through the terminal unit when the terminal unit fan is off.

  • Low primary-air temperatures can require heavily insulated ducts; however, using neutral air temperatures minimizes this requirement and prevents overcooling of some spaces.

  • In-room terminal units without central ventilation air may result in greater infiltration levels due to numerous penetrations of the exterior of the building, which must be sealed adequately to prevent air infiltration and water intrusion. This may be accentuated in winter conditions, when wind pressures and stack effects become more significant.

  • Adding necessary humidity in the winter is difficult.

  • Maintenance must be done within the occupied space, which may disrupt space use.

 Heating and Cooling Calculations

Basic calculations for airflow, temperatures, relative humidity, loads, and psychrometrics are covered in Chapters 1, 17, and 18 of the 2017 ASHRAE Handbook—Fundamentals. Use caution in determining peak load conditions for each space served by a terminal unit. Rather than depending on guidelines for typical lighting, ventilation, infiltration, equipment, and occupancy levels, the designer should try to get realistic values based on the particular owner’s use plans for the facility. If the client has an existing or similar facility, visiting it to understand the actual occupancy hours, concentration of equipment, and occupancy should help avoid unrealistic assumptions. Incorporating effects of planned energy-saving features (e.g., daylighting; high-efficiency/low-heat-producing lighting; shading apparatus for privacy, glare, or solar radiant control; fan and outdoor air modulation; full-building energy management control strategies) can prevent oversizing of terminal units and resulting potential loss of humidity control. Determining areas where the normal base load will be a small percentage of the concentrated usage load and understanding the usage schedule for the area can allow equipment selection and control strategies to maximize energy savings and still provide excellent comfort control in both extremes.

For example, in a zone with a terminal unit sized for 7000 Btu/h (common for offices), a simple change of four 100 W incandescent light bulbs to compact fluorescents could reduce the space’s heat load by about 18% of the unit’s capacity. If this is the consistent peak load of the space for future years, the terminal unit is oversized. Unless a central ventilation pretreatment system handles the entire latent load of the space and the outdoor air, humidity control will be lost in the space.

Integrated building design (IBD) techniques should be used to ensure the building envelope provides adequate energy efficiency, airtightness, and moisture penetration control to allow terminal units to control the indoor environmental conditions without need for excessive moisture control in each space. Close cooperation of all parties during design is necessary to create an overall building design that minimizes the required mechanical systems’ energy consumption while achieving good indoor conditions. For details on IBD, see Chapter 58 of the 2019 ASHRAE Handbook—HVAC Applications.

Computer programs generally can model primary ventilation systems as well as secondary in-room terminal systems. Most, however, do not allow the user to assign the room latent load as part of the primary ventilation system capacity requirement. Therefore, the designer needs to either manually determine final capacity requirements for both the primary and in-room units, or use overrides and manual inputs to redistribute the loads within the computer program after initial sensible and latent loads as well as block and peak conditions have been determined.

The design refrigeration load is determined by considering the entire portion or block of the building served by the air-and-water system at the same time. Because the load on the secondary-water system depends on the simultaneous demand of all spaces, the sum of the individual room or zone peaks is not considered.

 Space Heating

Some in-room terminal units provide only heating to the end space. Equipment such as cabinet or unit heaters, radiant panels, radiant floors, and finned-tube radiators are designed for heating only. Extreme care must be used with these systems if they are incorporated into a two-pipe changeover piping distribution system, or any other system in which secondary water being piped is not consistently over 100°F. The heating coils in these units are not designed to handle condensation, and there is no drain pipe in the unit. If cold water is provided to these units, dripping condensation from units, valves, or piping may damage building finishes or saturate the insulation, leading to mold growth. Ball valves tied into the automatic temperature control (ATC) system and/or aquastats should be provided to prevent water at temperatures below space air dew point from reaching heating-only terminal units.

 Central (Primary-Air) Ventilation Systems

Generally, the supply air volume from the central apparatus is constant and is called primary or ventilation air to distinguish it from recirculated room air or secondary air. The quantity of primary air supplied to each space is determined by the amount of outdoor air required by codes and other applicable guidelines for ventilation. If in-room terminal units are heating-only units, then the primary-air system must also provide the required sensible cooling capacity at maximum room cooling load. The air may be from outdoors, or may be mixed outdoor and return air. During the cooling season, air is dehumidified sufficiently in the central conditioning unit to maintain required humidity conditions and to prevent condensation on the in-room terminal unit cooling coil. (Both outdoor air and space latent loads should be handled by the central unit.) Centrally supplied air can be supplied at a low enough dew point to absorb moisture generated in the space, but as a minimum should be supplied at a condition so that the room terminal unit has to remove only the space-generated latent load (this is only appropriate with unit ventilators with the capability to handle the latent space loads). In winter, moisture can be added centrally to limit dryness.

As the primary air is dehumidified, it is also cooled. The air should be cool enough when delivered to offset part of the room sensible loads without overcooling the spaces. If the necessary amount of cooling (i.e., that needed to dehumidify primary air to handle all of the space and outdoor air latent loads) is likely to overcool the end spaces, the primary air should be reheated to minimize any overcooling possibilities. A heating coil located in the reheat position may be required in the central (primary) air handler, as well as a preheater in areas with freezing weather. Alternatively, reheating can occur at the terminal units, where only a minimal number of spaces might be overcooled.

When outdoor air is introduced from a central ventilation system, it may be connected to the inlet plenum of some in-room terminal units (fan-coils, unit ventilators, active chilled beams, or induction units), or introduced directly into the space. If introduced directly, ensure that this air is pretreated, dehumidified, and held at a temperature approximately equal to room temperature so as not to cause occupant discomfort when the space unit is off. Caution should always be used to prevent overcooling or loss of humidity control from ventilation air, which can lead to condensation problems on surfaces as well as discomfort for occupants.

In the ideal in-room terminal unit design, the cooling coil is always dry, greatly extending terminal unit life and eliminating odors and the possibility of bacterial growth in the unit in the occupied space, as well as limiting condensation issues in the spaces. In this case, in-room terminals may be replaced by radiant panels (see Chapter 6) or chilled beams and panels, as the primary air controls the space humidity. Therefore, the moisture content of primary air must be low enough to offset the room’s latent heat gain and to maintain a room dew point low enough to preclude condensation on the secondary cooling surface.

Even though some systems operate successfully with little or no condensate, a condensate drain is recommended. In systems that shut down during off hours, start-up load may include a considerable dehumidification load, producing moisture to be drained away. In climates with elevated outdoor air dew points during space-cooling periods, piped condensate removal systems that can be maintained regularly should always be included.

 Central Plant Sizing

Central equipment size is based on the block load of the entire building at the time of the building peak load, not on the sum of individual in-room terminal unit peak loads. Cooling load should include appropriate diversity factors for lighting and occupant loads. Heating load is based on maintaining the unoccupied building at design temperature, plus an additional allowance for pickup capacity if the building temperature is set back at night. For additional information, see Chapter 3.

If water supply temperatures or quantities are to be reset at times other than at peak load, the adjusted settings must be adequate for the most heavily loaded space in the building. Analysis of individual room load variations is required.

If the side of the building exposed to the sun or interior zone loads requires chilled water in cold weather, consider using condenser water with a water-to-water heat exchanger or a four-pipe system. Varying refrigeration loads require the water chiller to operate satisfactorily under all conditions.

 Building Pressurization

As with any HVAC system, the amount of ventilation air required depends on the number of occupants in the space as well as other factors (see ASHRAE Standard 62.1). The rate of airflow per person or per unit area is also usually dictated by state codes, based on activity in the space and contaminant loads. If the amount of ventilation air required is considerable (i.e., 10% or more of a space’s total supply air volume), the designer needs to consider how the excess air will move out of the space and the building. Means of preventing overpressurization may have to be provided, depending on building tightness, amount of exhaust, and other considerations. Additionally, the designer should consider heat recovery for the rejected air.

 First, Operating, and Maintenance Costs

As with all systems, the initial cost of an in-room terminal system varies widely, depending on location, local economy, and contractor preference (even for identical systems). For example, a through-wall unit ventilator system is less expensive than fan-coil units with a central ventilation system, because it does not require extensive ductwork distribution. The operating cost depends on the system selected, the designer’s skill in selecting and correctly sizing components, and efficiency of the duct and piping systems. A terminal unit design without a central ventilation system is often one of the less expensive systems to install, but in most situations will not operate without some condensation and humidity issues.

Because in-room terminal equipment is in each occupied space, maintenance may be more time consuming, depending on the size of the facility. The equipment and components are less complex than other equipment. A common method of repairing in-room terminal units is to simply disconnect and replace a nonfunctioning unit, minimizing the time spent in the occupied space. The nonfunctioning unit can then be repaired in a workshop and used as a spare. The number of individual units is much greater than in many systems, therefore increasing the number of control valves. If a building automation system (BAS) is used, the number of control points is increased as well, which raises the first cost and maintenance costs of the controls.

 Energy

The engineer’s early involvement in design of any facility can considerably reduce the building’s energy consumption; collaboration between the architect and engineer allows optimization of energy conservation measures, including the building envelope, as well as selection of an HVAC system that is energy efficient with minimal operational costs. In practice, however, a system might be selected based on low first cost or to perform a particular task. In general, terminal units can save energy if the BAS controls operation of the units and can deenergize them if the space is unoccupied. This adds significant cost to the control system, but can save on operational costs. If a central ventilation system is used, energy recovery in the air handler should be considered to minimize operation costs.

The choice of two- or four-pipe piping system and the design of the piping system is another energy-impacting decision. Pumping horsepower, insulation to control heat losses, and the number of yearly changeovers all affect the appropriateness and available energy savings of each type of piping system.

 Life-Cycle Costs

Life-cycle costs include the first, operational, maintenance, and replacement costs over a predetermined length of time. With an in-room terminal system, a major portion of the cost of the system is the insulated piping infrastructure needed to provide the primary and secondary equipment with water (or refrigerant). When properly selected, installed, and maintained, these components have a very long expected life. The in-room terminal units are generally of simple design and complexity and can be readily repaired. As a general rule, the less condensate that occurs at the in-room units, the longer their life span. Selection of good-quality central ventilation equipment can result in quite lengthy life spans for these units. Operational concerns that affect costs are discussed throughout this chapter. Consult Chapter 37 of the 2019 ASHRAE Handbook—HVAC Applications for more information on equipment life expectancies and predicting maintenance costs.

2. SYSTEM COMPONENTS AND CONFIGURATIONS

 Components

Terminal units have common components; mainly, a fan, coil(s), filter, dampers, and controls (although some units only have coils and controls).

 Damper.
 If a terminal unit is providing ventilation air through the envelope of the building, a damper is needed to stop airflow when the room is in unoccupied status. Because in-room terminal units often have a ducted primary- or central ventilation air system, a damper on the primary system duct allows airflow to be balanced. Many less expensive in-room terminal units have manual dampers rather than automatic. Regardless of whether dampers are manually operated or automatic, pressurization problems can occur because of damper position compared with exhaust fan operation and primary air system operation, so the designer needs to carefully coordinate how building pressurization is controlled and maintained.
 Filtration.
 Filtration capabilities with in-room terminals are generally minimal. The cabinet and component assembly often provide very little ability to improve the filtration capability, although fan-coil-style terminal units commonly can handle better filtration. Manufacturer-supplied filters are often either washable or throwaway filters. Some manufacturers provide an option for a higher-quality pleated-style filter to be used, but their recommendations for motor selection should be obeyed. Maintenance instructions for washable filters should be carefully followed, to avoid filter impaction and reduced airflow; good filter maintenance improves sanitation and provides full airflow, ensuring full-capacity delivery.
 Heating and Cooling Coils.
 Coils in terminal units are usually available in one-, two-, three-, and sometimes four-row coils for cooling and one- or two-row coils for heating. In units with untreated outdoor air, selecting coil and fin materials and coatings for longer life expectancy should be carefully considered (see Chapter 23). Only the building envelope and internal space heating and cooling loads need to be handled by in-room terminal units when outdoor air is adequately pretreated by a central system to a neutral air temperature of about 70°F. This pretreatment should reduce the size and cost of the terminal units. All loads must be considered in unit selection when outdoor air is introduced directly through building apertures into the terminal unit, as is sometimes done with unit ventilators. For cold climates, coil freeze protection must be considered.
 Fan.
 Terminal units typically are not complex. Some larger units serving multiple spaces may have a variable-speed drive (VSD) or other speed control on the fan.
 Duct Distribution.
 Terminal units work best without extensive ductwork. With ducts, static pressure on the fan (instead of the coil capacity) may be the determining factor for sizing the terminal units, because multiple fan selections are not normally available.
 Automatic Controls.
 Most terminal units are controlled with a standard electronic thermostat, either provided by the manufacturer or packaged by the automatic temperature controls (ATC) contractor. Thermostats capable of seven-day programming and night setback can improve energy savings where space usage is predictable enough to allow consistent programs. Terminal units can be incorporated into a BAS, but the cost to do so may be prohibitive, depending on the number of terminal units in the building. The potential operational cost savings, especially in facilities where a significant percentage of areas are often unoccupied, should be evaluated against the first-cost consideration.
 Capacity Control.
 Terminal unit capacity is usually controlled by coil water or refrigerant flow, fan speed, or both. Water flow can be thermostatically controlled by return air temperature or a wall thermostat and two- or three-way valve. Unit controls may be a self-contained direct digital microprocessor, line voltage or low-voltage electric, or pneumatic. Fan speed control may be automatic or manual; automatic control is usually on/off, with manual speed selection. Room thermostats are preferred where automatic fan speed control is used. Return air thermostats do not give a reliable index of room temperature when the fan is off or when outdoor air is introduced nearby. Residential fan-coil units may have manual three-speed fan control, with water temperature (both heating and cooling) scheduled based on outdoor temperature. On/off fan control can be poor because (1) alternating shifts in fan noise level are more obvious than the sound of a constantly running fan, and (2) air circulation patterns in the room are noticeably affected. However, during cooling cycles, constant fan operation results in higher relative humidity levels than fan cycling, unless all latent load is handled by a primary central ventilation system.

For systems without primary central ventilation, summer room humidity levels tend to be relatively high, particularly if modulating chilled-water control valves are used for room temperature control. Alternatives are two-position control with variable-speed fans (chilled water is either on or off, and airflow is varied to maintain room temperature) and the bypass unit variable chilled-water temperature control (chilled-water flow is constant, and face and bypass dampers are modulated to control room temperature).

The designer must be careful to understand the unit’s operating conditions for the vast majority of the operation hours, and how the unit will actually perform at those times. Many manufacturers publish sensible and latent capacity information that is developed from testing at a single set of conditions (generally the AHRI standard condition), then use computer modeling or extrapolation rather than actual testing to determine operation capacities at other conditions. In most situations, the unit’s actual operation for the vast majority of time is at conditions other than the rating condition. Additionally, control choices for water flow or airflow may create conditions different from those used by the manufacturer to determine the published operation capacities. Because peak conditions are often used to select coils but in most applications only occur a small percentage of the time, oversizing of coils and loss of humidity control become common if these issues are not carefully thought through during design and selection of the equipment.

 Configurations

Terminal units are available in many different configurations; however, not all configurations are available for all types of terminal units. The designer should evaluate the air pathways of the specific units being considered, because some allow raw outdoor air to bypass the filter and/or the coils. Additionally, on some unit ventilators with face and bypass, the raw outdoor air is allowed to stratify in the bypass section, again bypassing the coils. Depending on climate conditions and filtration requirements, these configurations may not be appropriate.

Low-profile vertical units are available for use under windows with low sills; however, in some cases, the low silhouette is achieved by compromising features such as filter area, motor serviceability, and cabinet style.

Floor-to-ceiling, chase-enclosed units are available in which the water and condensate drain risers are part of the factory-furnished unit. Stacking units with integral prefabricated risers directly one above the other can substantially reduce field labor for installation, an important cost factor. These units are used extensively in hotels and other residential buildings. For units serving multiple rooms (single-occupancy suite-type spaces), the supply and return air paths must be isolated from each other to prevent air and sound interchange between rooms.

Perimeter-located units give better results in climates or buildings with high heating requirements. Heating is enhanced by under-window or exterior wall locations. Vertical units with finned risers can operate as convectors with the fans turned off during night setback, and overheating can become an issue.

Horizontal overhead units may be fitted with ductwork on the discharge to supply several outlets. A single unit may serve several rooms (e.g., in an apartment house where individual room control is not essential and a common air return is feasible). Units must have larger fan motors designed to handle the higher static pressure resistance of the connected ductwork.

Horizontal models conserve floor space and usually cost less, but when located in furred ceilings, they can create problems such as condensate collection and disposal, mixing return air from other rooms, leaky pans damaging ceilings, and difficult access for filter and component removal. In addition, possible condensate leakage may present air quality concerns.

Other sections in this chapter discuss specific configurations for the type of unit, and indicate additional chapters in the volume that provide diagrams and additional information.

3. SECONDARY-WATER DISTRIBUTION

The secondary-water system includes the part of the water distribution system that circulates water to room terminal units when the water has been cooled or heated either by extraction from or heat exchange with another source in the primary circuit. In the primary circuit, water is cooled by flow through a chiller or is heated by a heat input source. Water flow through the in-room terminal unit coil performs secondary cooling or heating when the room air (secondary air) gives up or gains heat. Secondary-water system design differs for two- and four-pipe systems. Secondary-water systems are discussed in Chapter 13.

4. PIPING ARRANGEMENTS

For terminal units requiring chilled and/or hot water, the piping arrangement determines the performance characteristics, ease of operation, and initial cost of the system. Each piping arrangement is briefly discussed here; for further details, see Chapter 13.

 Four-Pipe Distribution

Four-pipe distribution of secondary water has dedicated supply and return pipes for chilled and hot water. The four-pipe system generally has a high initial cost compared to a two-pipe system but has the best system performance. It provides (1) all-season availability of heating and cooling at each unit, (2) no summer/winter changeover requirement, (3) simpler operation, and (4) hot-water heating that uses any heating fuel, heat recovery, or solar heat. In addition, it can be controlled at the terminal unit to maintain a dead band between heating and cooling so simultaneous heating and cooling cannot occur.

 Two-Pipe Distribution

 Two-Pipe Changeover Without Central Ventilation.
 In this system, either hot or cold water is supplied through the same piping. The terminal unit has a single coil. The simplest system with the lowest initial cost is the two-pipe changeover with (1) outdoor air introduced through building apertures, (2) manual three-speed fan control, and (3) hot- and cold-water temperatures scheduled by outdoor temperatures. The changeover temperature is set at some predetermined set point. If a thermostat is used to control water flow, it must reverse its action depending on whether hot or cold water is available.

The two-pipe system cannot simultaneously provide heating and cooling, which may be required during intermediate seasons when some rooms need cooling and others need heat. This characteristic can be especially troublesome if a single piping zone supplies the entire building, but may be partly overcome by dividing the piping into zones based on solar exposure. Then each zone may be operated to heat or cool, independent of the others. However, one room may still require cooling while another room on the same solar exposure requires heating, particularly if the building is partially shaded by an adjacent building or tree.

Another system characteristic is the possible need for frequent changeover from heating to cooling, which complicates operation and increases energy consumption to the degree that it may become impractical. For example, two-pipe changeover system hydraulics must consider the water expansion (and relief) that occurs during cycling from cooling to heating.

Caution must be used when this system is applied to spaces with widely varying internal loads, and outdoor air is introduced through the terminal unit instead of through a central ventilation system. Continuous introduction of outdoor air when the load is reduced often results in sporadically unconditioned outdoor air, which can cause high space humidity levels, unless additional separate dehumidification or reheat is used. The outdoor air damper in the unit must be motor-operated so it can be closed during unoccupied periods when minimal cooling is required.

The designer should consider the disadvantages of the two-pipe system carefully; many installations of this type waste energy and have been unsatisfactory in climates where frequent changeover is required, and where interior loads require cooling and exterior spaces simultaneously require heat.

 Two-Pipe Changeover with Partial Electric Strip Heat.
 This arrangement provides heating in intermediate seasons by using a small electric strip heater in the terminal unit. The unit can handle heating requirements in mild weather, typically down to 40°F, while continuing to circulate chilled water to handle any cooling requirements. When the outdoor temperature drops sufficiently to require heating beyond the electric strip heater capacity, the water system must be changed over to hot water.
 Two-Pipe Nonchangeover with Full Electric Strip Heat.
 This system may not be recommended for energy conservation, but it may be practical in areas with a small heating requirement or in other situations where life-cycle costs support this choice.

 Three-Pipe Distribution

Three-pipe distribution uses separate hot- and cold-water supply pipes. A common return pipe carries both hot and cold water back to the central plant. The terminal unit control introduces hot or cold water to the common unit coil based on the need for heating or cooling. This type of distribution is not recommended because of its energy inefficiency from constantly reheating and recooling water, and it does not comply with most recognized energy codes.

 Condenser Water Systems with Heat Pump Terminal Units

Condenser water systems are very similar to the two-pipe changeover with partial electric strip heat. The supply and return pipes carry water at more moderate temperatures than those of typical chilled or hot water. The heat pumps use the water as a heat source for heating and as a heat sink in cooling mode, allowing various in-room heat pumps to meet room needs during intermediate seasons. If additional heat is needed in a room, a small electric strip heater in the terminal unit can provide it. When the outdoor temperature drops sufficiently to require additional heating capacity, the water system must be changed over to hot water. Chapters 9, 14, and 49 contain additional information about condenser water piping systems and heat pumps.

5. FAN-COIL UNIT AND UNIT VENTILATOR SYSTEMS

Fan-coil units and unit ventilator systems are similar; their common traits and differences are discussed here. Both (1) can provide cooling as well as heating, (2) normally move air by forced convection through the conditioned space, (3) filter circulating air, and (4) may introduce outdoor ventilation air. Fan-coils are available in various configurations to fit under windowsills, above furred ceilings, in vertical pilasters built into walls, etc., whereas unit ventilators are available in three main configurations: floor-mounted below a window, horizontal overhead with ducted supply and return, and stacking vertical units. Fan-coils are often used in applications where ventilation requirements are minimal. Unit ventilators are similar, except that unit ventilators are designed to provide up to 100% outdoor air to the space.

Basic elements of both fan-coil and unit ventilator units are a finned-tube heating/cooling coil, filter, and fan section (Figure 1). Unit ventilators can include a face-and-bypass damper. The fan recirculates air from the space through the coil, which contains either hot or chilled water. The unit may contain an additional electric resistance, steam, or hot-water heating coil. The electric heater is often sized for fall and spring to avoid changeover problems in two-pipe systems; it may also provide reheat for humidity control. A cleanable or replaceable moderate-efficiency filter upstream of the fan helps prevent clogging of the coil with dirt or lint entrained in recirculated air. It also helps protect the motor and fan, and can reduce the level of airborne contaminants in the conditioned space. The fan and motor assembly is arranged for quick removal for servicing. The units generally are also equipped with an insulated drain pan.

Typical Fan-Coil Unit

Figure 1. Typical Fan-Coil Unit


Most manufacturers furnish units with cooling performance certified as meeting Air-Conditioning, Heating, and Refrigeration Institute (AHRI) standards. Unit prototypes have been tested and labeled by Underwriters Laboratories (UL) or Engineering Testing Laboratories (ETL), as required by some codes. Requirements for testing and standard rating of room fan-coils with air-delivery capacities of 1500 cfm or below are described in AHRI Standard 440 and ASHRAE Standard 79. Requirements for testing and standard rating of room unit ventilators with air delivery capacities of 3000 cfm or below are described in AHRI Standard 840.

For the U.S. market, fan-coil units are generally available in nominal sizes of 200, 300, 400, 600, 800, and 1200 cfm, and unit ventilators in nominal sizes of 750, 1000, 1500, and 2000 cfm. Both types of units can often be purchased with multispeed, high-efficiency fan motors.

 Types and Location

Floor-mounted units have various ventilation air ductwork connections, including from the back or a ducted collar on the top of the cabinet. Ceiling-mounted and stacking units can be mounted completely exposed, partially exposed in a soffit, fully recessed, or concealed. Ventilation air connections can be made in the back or top of the unit.

For existing building retrofit, it is often easier to install piping and wiring for a terminal unit system than the large ductwork required for an all-air system. Common fan-coil system applications are hotels, motels, apartment buildings, and office buildings. Fan-coil systems are used in many hospitals, but they are less desirable because of the low-efficiency filtration and difficulty in maintaining adequate cleanliness in the unit and enclosure. In addition, limits set by the American Institute of Architects’ Guidelines for Design and Construction of Hospital and Health Care Facilities (AIA 2001) do not allow air recirculation in certain types of hospital spaces.

Unit ventilator systems are most frequently used in classrooms, which need a high percentage of outdoor air for proper ventilation. Unit ventilators are often located under a window along the perimeter wall. They are available in a two-pipe configuration with changeover, two-pipe with electric heating, four-pipe, or with heating and DX coils for spaces (e.g., computer rooms) that may require year-round cooling. Limited ductwork may be allowed, allowing for higher and often exposed ceiling systems. These units can often be misused as shelving in classroom; books and paperwork may be stacked on top of them, impeding airflow to the space. Also, ventilation air intake louvers can become choked by vegetation if they are not properly maintained. In addition, because the fans are sized to accommodate 100% ventilation air, they are typically noisier than fan-coils, although recent developments have led to new units that are much quieter.

For existing building retrofit, it is easiest to replace unit ventilators in kind. If a building did not originally use unit ventilators, installing multiple ventilation air intake louvers to accommodate the unit ventilators may be cost prohibitive. Likewise, installing a different type of system in a building originally fitted with unit ventilators requires bricking up intake louvers and installing exposed ductwork (if there is no ceiling plenum) or creating a ceiling space in which to run ductwork. Unit ventilators are best applied where individual space temperature control with large amounts of ventilation air is needed.

 Ventilation Air Requirements

Fan-coil and unit ventilators often receive ventilation air from a penetration in the outer wall or from a central air handler. Units that have outdoor air ducted to them from an aperture in the building envelope are not suitable for tall buildings because constant changes in wind pressure cause variations in the amount of outdoor air admitted. In this situation, ventilation rates can also be affected by stack effect, wind direction, and speed. Also, freeze protection may be required in cold climates, because preheating outdoor air is not possible. Historically, fan-coils have often been used in residential construction because of their simple operation and low first cost, and because residential rooms were often ventilated by opening windows or by outer wall apertures rather than a central system. Operable windows can cause imbalances with a ducted ventilation air system; current standards have moved toward requiring specific ventilation airflow control in residences, therefore minimizing the ability to use noncentralized ventilation systems, even in residential applications.

Unlike fan-coils, unit ventilators can provide the entire volume of ventilation air that is required in many applications. The heating/cooling coils in unit ventilators therefore differ considerably from fan-coils. Coils in unit ventilators are much deeper, because the unit ventilator needs to be able to heat, cool, and dehumidify up to 100% ventilation air. Coil selection must be based on the temperature of the entering mixture of primary and recirculated air, and air leaving the coil must satisfy the room’s sensible and latent cooling and heating requirements. If variable occupancy levels regularly occur during system operation hours, such as often occurs with classrooms, sizing a single unit for the fully occupied outdoor air requirement could result in oversized cooling capacity during many hours of operating time. This could result in loss of humidity control. For variable-occupancy applications, demand control ventilation or pretreated outdoor air is recommended.

 Selection

Some designers select fan-coil units and unit ventilators for nominal cooling at medium speed when a three-speed control switch is provided, to enable quieter operation in the space and add a safety factor (sensible capacity can be increased by operating at high speed). Sound power ratings are available from many manufacturers.

If using a horizontal overhead unit with ducted supply and return, fan capacity may be the factor that decides the unit’s size, not the coil’s capacity. Static pressure as little as 0.3 in. of water can significantly affect fan air volume and unit capacity.

If the unit is selected to provide full capacity at medium speed, the unit must also be able to handle the full volume of required ventilation air at that airflow. If cooling loads vary more than 20% during operation hours, it is highly likely this selection could result in oversized capacity operation and loss of humidity control. Current fan motor speed control options, such as electronically commutated motors (ECMs), and units designed to operate more quietly allow unit selection for the fan’s full-speed total capacity, and minimize the chance of oversizing.

 Wiring

Fan-coil and unit ventilator blower fans are driven by small motors. Fan-coil motors are generally shaded pole or capacitor start with inherent overload protection. Operating wattage of even the largest sizes rarely exceeds 300 W at high speed. Running current rarely exceeds 2.5 A. Unit ventilator motors are typically 1/2 hp or less. Operating power of even the largest sizes rarely exceeds 400 W at high speed. Almost all motors on units in the United States are 120 V, single-phase, 60 Hz current.

In planning the wiring circuit, follow all required codes. The preferred wiring method generally provides separate electrical circuits for fan-coil or unit ventilator units and does not connect them into the lighting circuit, or other power circuits. Separate wiring connections may be needed for condensate pumps.

 Condensate

Even when outdoor air is pretreated, a condensate removal system should be installed for fan-coil units and unit ventilators. Drain pans should be integral for all units. For floor-mounted units along the perimeter of the building, condensate piping can run from the drain pan to the exterior grade. Where drainage by gravity will not be sufficient, provide condensate pumps. Condensate drain lines should be properly sized and maintained to avoid clogging with dirt and other materials. Condensation may occur on the outside of drain piping, which requires that these pipes be insulated. Many building codes have outlawed systems without condensate drain piping because of the potential damage and possibility of mold growth in stagnant water accumulated in the drain pan.

 Capacity Control

Fan-coil and unit ventilator capacity is usually controlled by coil water flow, fan speed, or a combination of these. In addition, unit ventilators often are available with a face-and-bypass damper, which allows for another form of capacity control. For additional information, see the discussion on capacity control in the section on System Components and Configurations.

 Maintenance

Fan-coil and unit ventilator systems require more maintenance than central all-air systems, and the work must be done in occupied areas. Units operating at low dew points require regular (multiple times per year) cleaning and flushing of condensate pans and drains to prevent overflow and microbial build-up. Coils should be cleaned at least once a year, and more often when they consistently are removing moisture. The physical restraints of in-room terminal units located high in rooms or concealed in ceilings, soffits, etc., can create challenges for proper coil cleaning. Water valves, controls, and dampers should also be checked yearly for proper calibration, operation, and needed repairs.

Filters are small and low-efficiency, and require frequent changing to maintain air volume. Cleaning frequency varies with the application. Units in apartments, hotels, and hospitals usually require more frequent filter service because of lint. Unit motors may require periodic lubrication. Motor failures are not common, but when they occur, the entire fan can be quickly replaced with minimal interruption in the conditioned space. More specialized motors with speed control devices may take several days to get a replacement, so large facilities should stock several spares for quick replacement to avoid significant down time for the unit. Chapters 20 and 28 provide more information on fan-coils and unit ventilators, respectively.

6. VARIABLE-REFRIGERANT-FLOW (VRF) UNITS

Technological advances in compressor design and control as well as use of electronically controlled expansion valves have allowed design of DX systems in which a single compressor unit provides refrigerant to multiple in-room terminal units. These types of systems are commonly called variable-refrigerant-flow (VRF) systems. Configuration of in-room units is similar to fan-coils, but uses a DX coil instead of water.

In these systems, refrigerant piping to terminal units is also called primary piping, and the compressor unit can often be more than 100 ft from the in-room terminal units.

To allow heating to occur in one space while cooling occurs in an adjacent space, heat pump/heat recovery condensing units must be used and a set of three refrigerant pipes (suction, liquid, and hot gas) must be piped out into the building to the in-room terminal units. A reversing valve must be provided for each of the in-room terminal units, to allow them to use either liquid refrigerant to cool, or hot gas to heat. The specifics of long-run refrigerant piping are discussed further in Chapter 1 of the 2018 ASHRAE Handbook—Refrigeration, and most manufacturers of these type of systems have very specific installation instructions that must be followed. As with any system that runs refrigerant piping through occupied areas of a building, ASHRAE Standard 15 must be complied with, as well.

VRF systems are discussed in more detail in Chapter 18.

7. CHILLED-BEAM SYSTEMS

Chilled beams are an evolution of chilled ceiling panels. Reports of energy savings over variable-air-volume (VAV) systems, especially in spaces with high concentrations of sensible loads (e.g., laboratories), have been touted in Europe and Australia. Applications such as health care, data centers, and some office areas may be well suited to chilled-beam systems.

Two types of chilled beams, passive and active, are in use (Figure 2). Passive chilled beams consist of a chilled-water coil mounted inside a cabinet. Chilled water is piped to the convective coil at between 58 and 60°F. Passive beams use convection currents to cool the space. As air that has been cooled by the beam’s chilled-water coil falls into the space, warmer air is displaced, rises into the coil, and is cooled. Passive beams can provide approximately 400 Btu/ft and, to ensure proper dehumidification and effective ventilation to the spaces, require a separate ventilation system to provide tempered, dehumidified air. Heat can be provided by finned-tube radiation along the space perimeter. Overcooling must be avoided during cooling seasons, to prevent discomfort, condensation, and microbial growth in spaces. Active chilled beams can provide up to approximately 800 Btu/ft. They operate with induction nozzles that entrain room air and mix it with the primary or ventilation air that is ducted to the beam. Chilled water is piped to the coil at between 55 and 60°F. Primary air should be ducted to the beam at 55°F or lower to provide proper dehumidification. The primary air is then mixed with induced room air at a ratio of 1:2. For example, 50 cfm of primary air at 55°F may be mixed with 100 cfm of recirculated room air, and the active beam would distribute 150 cfm at around 65°F. If the low-temperature primary air alone will overcool spaces during any time of the year, there must be provision for reheat. Active beams can have either a two- or four-pipe distribution system. The two-pipe system may be cooling only or two-pipe changeover. Active beams can be designed to heat and cool the occupied space, but finned-tube radiation is still commonly used to provide heating in a space that is cooled with active beams.

Passive and Active Chilled-Beam Operation (Courtesy of Trox USA, Inc.)

Figure 2. Passive and Active Chilled-Beam Operation
(Courtesy of Trox USA, Inc.)


Both active and passive beams are designed to operate dry, without condensate. In some models of active beams, a drain pan may be available if the coil is in a vertical configuration. Horizontal coils in passive beams cannot have drain pans, because the area directly below the coil is needed to allow the air in the convection current to circulate. Chilled beams can be used in various applications; however, they are best used in applications with high sensible loads, such as laboratory spaces with high internal heat gains. See manufacturers’ information for beam cooling capacities at various water temperatures and flow rates. Several manufacturers have design guides available on the Internet.

The latest generation of chilled beams is multiservice: they can be either passive or active, and combine building operations such as lighting, security sensors, motion detectors, sprinkler systems, smoke detectors, intercoms, and power or fiber-optic distribution with the chilled beam. Proper implementation requires extensive integrated building design.

 Types and Location

Passive beams are available in sections up to 10 ft long and 18 to 24 in. wide. They can be located above the ceiling with perforated panels below it, mounted into the frame of an acoustical tile ceiling, or mounted in the conditioned space. The perforated panels must have a minimum 50% free area and extend beyond either side of the beam for usually half of the unit’s width, so the convection current is not hindered. Also, care must be taken to not locate passive beams too close to window treatments, which can also hinder air movement around the beam.

Active beams are available in sections up to 10 ft long and 12 to 24 in. wide. They can be mounted into the frame of an acoustical tile ceiling or in the conditioned space.

 Ventilation Air Requirements

Passive beams require a separate ventilation system to provide tempered and dehumidified air to the space. The ventilation air should be ducted to low-wall diffusers or in an underfloor distribution system so that the ventilation air does not disturb the convection currents in the conditioned space. Ventilation air can be ducted directly into the active beams. If more ventilation air is needed to meet the space requirements, the volume of air can be split by the active beams and high-induction diffusers. Care must be taken in selecting diffuser locations to coordinate well with the convective currents required by the chilled beams.

 Selection

Chilled beams are selected based on the calculated heat gain for the space less the cooling effect of the primary ventilation air.

 Wiring

Chilled beams only require controls wiring. There is no fan or other electrical equipment to be wired.

 Condensate

Chilled beams are designed to operate dry, with few exceptions. In some active beams with vertical coils, a drain pan may be installed. However, as a rule, a separate ventilation system should be sized to handle the latent cooling load in the space, and the relative humidity should be closely monitored. If the primary ventilation system fails to properly control the space humidity, condensation may form on the beams and their housings. Dripping of this condensate could damage building materials and contents.

Chilled-water valves should have drain pans to contain any normal condensate that occurs, when the space is properly dehumidified. In case of loss of humidity control of the space, unpiped condensate drain pans will not be sufficient to avoid overflows and damage.

 Capacity Control

Capacity of the chilled beam is controlled by a two-way valve on the chilled-water pipe, which is wired to a room thermostat. There is typically one valve per zone (e.g., office, lecture hall). Beams should be piped directly in a reverse/return piping design. Beams are not typically piped in series.

 Maintenance

Maintenance on chilled beams requires blowing off the coils on a regular basis. Because coils are located throughout occupied spaces, this requires some coordination with occupants and housekeeping personnel to minimize effects on furniture and space contents.

 Other Concerns

Consistent air movement with natural convection equipment is difficult to achieve. The designer should consult with the manufacturer to determine the proper spacing of chilled beams based on ceiling height, heat generation sources, occupant locations, and movement patterns. Prevention of cold air ponding on the floor, especially when heat sources vary, can be paramount in maintaining comfort.

Occupant comfort is affected by more than temperature and humidity. Noise levels and nonstagnant air are also important. Some spaces may not achieve sufficient air movement or background noise to allow occupant comfort through use of passive chilled beams. Additionally, insufficient filtration of the air may occur without sufficient air movement and filtration devices in the space.

When introducing pretreated ventilation air to a space, be careful not to interfere with convection currents while still complying with the requirements of ventilation effectiveness and efficiency.

8. RADIANT-PANEL HEATING SYSTEMS

Radiant heating panels can use either hot water or electricity. The panels are manufactured in standard 24 by 24 or 24 by 48 in. panels that can be mounted into the frame of an acoustical tile ceiling or directly to an exposed ceiling or wall. Radiant panels are designed for all types of applications. They are energy efficient, providing a comfortable heat without lowering the moisture content of the room air the way heated air systems may. Occupants in a space heated by radiant heat are comfortable at lower room temperatures, which frequently reduces operational costs. See Chapter 6 for more information on these systems.

 Types and Location

Radiant panels are typically mounted on the ceiling near perimeter walls in a metal frame. Unlike finned-tube radiation, they do not limit furniture placement. Electric radiant panels are available from 250 to 750 W in standard single-phase voltages.

 Ventilation Air Requirements

Radiant panels provide space heating. Ventilation air must be supplied by a central ventilation unit that can provide tempered, humidity-controlled air to the space.

 Selection

Radiant panels are selected based on the calculated heat loss for the space.

 Wiring

Electric radiant panels are available in standard single-phase voltages. Panels are often prewired, including the ground wire, with lead wires housed in flexible metal conduit and connector for junction box mounting.

 Capacity Control

Panel capacity is usually controlled by coil water flow, or in the case of electric heat, capacity steps. Most radiant panels are controlled with a wall-mounted thermostat located in the space.

 Maintenance

Because they have no moving parts, radiant panels require little maintenance. Water flow control valves require periodic verification that they are operating correctly.

9. RADIANT-FLOOR HEATING SYSTEMS

Radiant-floor heat is best applied under a finished floor that is typically cold to the touch. Radiant-floor heat systems in the past used flexible copper pipe heating loops encased in concrete. Unfortunately, the soldered joints could fail or the concrete’s expansion and contraction or chemical composition could corrode the pipes, causing them to leak. However, new technologies include flexible plastic tubing (often referred to as PEX, or cross-linked polyethylene) to replace the old flexible copper tubing. PEX tubing is also available with an oxygen diffusion barrier, because oxygen entrained in the radiant heat tubing can cause corrosion on the ferrous connectors between the tubing and the manifold system. PEX tubing is also available in longer lengths than the flexible copper, which minimizes buried joints. The tubing is run back to a manifold system, which includes valves to balance and shut down the system and a small circulator pump. Multiple zones can be terminated at the same manifold.

Historically, radiant-floor heat was commonly designed for residential applications, when ventilation was provided by operable windows, and cooling was not mandatory. Like most other in-room terminal systems, the required ventilation air must be supplied by a central unit that can provide tempered and humidity-controlled air that allows comfort conditions in the space to be met. Common applications of radiant-floor heat systems include large open buildings, such as airplane hangars, where providing heat at the floor is more cost-effective than heating the entire volume of air in the space. Radiant-floor heat is becoming more common for preschools, elementary schools, exercise spaces, and other locations where children or adults sit or lie on floors. Water in the radiant-floor loop is often around 90°F, depending on the floor finish. This is a lower temperature than forced hot-air systems, and reduces the energy required to heat the building. Buildings that have high ceilings, large windows, or high infiltration rates or that require high air change rates may save energy by using radiant-floor heat.

Radiant-floor systems are commonly zoned by room. Each room may require multiple pipe circuits, depending on the room’s area and the manifold’s location. Maximum tubing lengths are determined based on tubing diameter and desired heat output. If tubing is installed in a slab on or below grade or over an unconditioned space, insulation should be incorporated to minimize heat losses. If a radiant-floor heat system is installed in a slab over a conditioned space, the radiant effect on that space must be considered as well.

See Chapter 6 for more information on radiant panel heating systems.

 Types and Location

Radiant-floor heating is located in the flooring or just below it with a heat-reflecting wrap. If the final floor finish is hardwood flooring, the radiant-floor piping can be installed in plywood tracks with a heat reflector, below the finished floor. Ensure that, as the final flooring is nailed down, the flexible tubing is not punctured. If the final floor is a ceramic tile or other surface requiring a poured concrete, the radiant floor can be laid out in the concrete, if hot-water systems are being used. Electric underfloor heating is also available, using a prefabricated mat that is applied on top of the subfloor and under with ceramic tile. Radiant-floor heating systems can also be mounted below the floor joists, with a heat reflector below the piping. This method is often used in renovations where removing existing flooring is not feasible.

 Ventilation Air Requirements

Ventilation air must be supplied by a central ventilation unit that can provide tempered, humidity-controlled air to the space.

 Selection

Spacing between rows of tubing that make up the radiant floor varies, depending on the heat loss of the space. Usually, the entire heat loss of the space is calculated and the tubing spaced accordingly. Another method is to place tubing closer together near the room’s perimeter and increase the spacing in the interior. This method is more time consuming, and the difference is only noticeable in large spaces. Supply water temperature in the tubing is determined based on the flooring materials’ resistance to heat flow; the temperature is higher for carpeting and a pad than for ceramic tile. The tubing is also available in different nominal diameters, the most common being 3/8 or 1/2 in.

 Wiring

Circulator pumps at the manifolds require power. Additional controls for zone control valves may be selected for either line voltage or low voltage.

 Capacity Control

Because radiant floors heat the mass of the floor, these systems are typically slow to respond to environmental changes. The circulator pumps start on a call for heat from a thermostat; however, rapid solar gains to a space with many windows could cause the space to overheat. Smart systems have been used to anticipate the needs of the space and overcome the thermal flywheel effects inherent to these types of systems. Smart systems anticipate the need for heating based on outdoor conditions and the conditions experienced in the recent past. They anticipate when set-point temperatures are about to be achieved and reduce heat generation, to minimize overshooting. They also learn patterns of operation that help overcome reasonably consistent daily solar gains.

 Maintenance

The circulator pumps, valves, controls, and manifolds are the only components requiring maintenance. Once the tubing is laid out, it should be pressure-tested for leaks; once covered, it is extremely difficult and/or expensive to access.

10. INDUCTION UNIT SYSTEMS

Induction units are very similar to active chilled beams, although they have mostly been replaced by VAV systems. Only the specific differences of higher-pressure air induction units will be discussed here. Primary air is supplied to an induction unit’s plenum at medium to high pressure. The acoustically treated plenum attenuates part of the noise generated in the unit and duct. High-velocity induction unit nozzles typically generate significant high-frequency noise. A balancing damper adjusts the primary-air quantity within limits.

Medium- to high-velocity air flows through the induction nozzles and induces secondary air from the room through the secondary coil. This secondary air is either heated or cooled at the coil, depending on the season, room requirement, or both. Ordinarily, the room coil does no latent cooling, but a drain pan without a piped drain collects condensed moisture from temporary latent loads such as at start-up. This condensed moisture then reevaporates when the temporary latent loads are no longer present. Primary and secondary (induced) air is mixed and discharged to the room.

Secondary airflow can cause induction-unit coils to become dirty enough to affect performance. Lint screens are sometimes used to protect these terminals, but require frequent in-room maintenance and reduce unit thermal performance.

Induction units are installed in custom enclosures, or in standard cabinets provided by the manufacturer. These enclosures must allow proper flow of secondary air and discharge of mixed air without imposing excessive pressure loss. They must also allow easy servicing. Although induction units are usually installed under a window at a perimeter wall, units designed for overhead installation are also available. During the heating season, the floor-mounted induction unit can function as a convector during off hours, with hot water to the coil and without a primary-air supply. Numerous induction unit configurations are available, including units with low overall height or with larger secondary-coil face areas to suit particular space or load needs.

Induction units may be noisier than fan-coil units, especially in frequencies that interfere with speech. On the other hand, white noise from the induction unit enhances acoustical privacy by masking speech from adjacent spaces.

In-room terminals operate dry, with an anticipated life of 15 to 25 years. Individual induction units do not contain fans, motors, or compressors. Routine service is generally limited to temperature controls, cleaning lint screens, and infrequently cleaning the induction nozzles.

In existing induction systems, conserving energy by raising the chilled-water temperature on central air-handling cooling coils can damage the terminal cooling coil, causing it to be used constantly as a dehumidifier. Unlike fan-coil units, the induction unit is not designed or constructed to handle condensation. Therefore, it is critical that an induction terminal operates dry.

Induction units are rarely used in new construction. They consume more energy because of the increased power needed to deliver primary air against the pressure drop in the terminal units, and they generate high-frequency noise from the induction nozzles. In addition, the initial cost for a four-pipe induction system is greater than for most all-air systems. However, induction units are still used for direct replacement renovation; because the architecture was originally designed to accommodate the induction unit, other systems may not be easily installed.

11. SUPPLEMENTAL HEATING UNITS

In-room supplemental heating units come in all sizes. Units can have either electric or hot-water heat, and sometimes steam; they can be surface-mounted, semirecessed, or recessed in the walls on the floor or horizontally along the ceiling. Baseboard radiation is usually located at the source of the heat loss, such as under a window or along a perimeter wall, and is usually rated for between 400 and 600 Btu/ft at 170°F. Other supplemental heating units include unit heaters, wall heaters, and cabinet heaters.

All supplemental heating units can be supplied with an integral or separate wall-mounted thermostat. If the heater is located low in the space, an integral thermostat is sufficient most of the time; however, if the unit is mounted horizontally near the ceiling, the thermostat should be wired so that it is located in the space, for accurate space temperature readings. In addition, units may have a summer fan option, which allows the fan to turn on for ventilation. Water flow to space supplemental heaters should be cut off anytime the water temperature to the coil is below 80°F, to avoid condensation and consequent damage or mold growth.

12. PRIMARY- AIR SYSTEMS

Figure 3 illustrates a primary-air system for in-room terminal systems. The components are described in Chapter 4. Some primary-air systems operate with 100% outdoor air at all times. In climates where moisture content is lower outdoors than indoors, systems using return air may benefit from a provision for operating with 100% outdoor air (economizer cycle) to reduce operating cost during some seasons. In some systems, when the quantity of primary air supplied exceeds the ventilation or exhaust required, excess air is recirculated by a return system common with the interior system. A good-quality filter (MERV = 8 to 10) is desirable in the central air treatment apparatus. If it is necessary to maintain a given humidity level in cold weather, a humidifier can usually be installed. Steam humidifiers have been used successfully. Water-spray humidifiers must be operated in conjunction with (1) the preheat coil elevating the temperature of the incoming air or (2) heaters in the spray water circuit. Water-spray humidifiers should be used with caution, however, because of the possible growth of undesirable organisms in untreated water. See Chapter 22 for additional information on humidifiers.

Primary-Air System

Figure 3. Primary-Air System


The primary-air quantity is fixed, and the leaving primary-air temperature varies inversely with the outdoor temperature to provide the necessary amount of heating or cooling and humidity control. Proper leaving-air temperature must be determined based on climatic conditions and the influence of the ventilation air quantity on the final space temperature and relative humidity. In cooling season, many climates require primary air to be cooled to a point low enough to dehumidify the total system (cooling coil leaving temperature about 50°F or less, and almost completely saturated) and then reheated to be provided at an appropriate temperature and humidity level. During winter, primary air is often preheated and supplied at approximately 50°F to provide cooling. All room terminals in a given primary-air preheated zone must be selected to operate satisfactorily with the common primary-air temperature.

The supply fan should be selected at a point near maximum efficiency to reduce power consumption, supply air heating, and noise. Sound absorbers may be required at the fan discharge to attenuate fan noise.

Reheat coils are required in a two-pipe system. Reheat may not be required for primary-air supply of four-pipe systems. Formerly, many primary-air distribution systems for induction units were designed with 8 to 10 in. of water static pressure. With energy use restrictions, this is no longer economical. Good duct design and elimination of unnecessary restrictions (e.g., sound traps) can result in primary systems that operate at 4.5 to 6.0 in. of water or even lower. Low-initial-cost, smaller ductwork has to be weighed against operating costs during life-cycle evaluation, to provide a system that best meets the owner’s long-term goals. Primary-air distribution systems serving fan-coil systems can operate at pressures 1.0 to 1.5 in. of water or lower. Induction units and active chilled beams require careful selection of the primary-air cooling coil and the induction unit nozzles to achieve an overall medium-pressure primary-air system. Primary-air system distribution that is independently supplied to spaces for use with other in-room terminal systems may be low-velocity or a combination of low- and medium-velocity systems. See Chapter 21 in the 2017 ASHRAE Handbook—Fundamentals for a discussion of duct design. Variations in pressure between the first and last terminals should be minimized to limit the pressure drop required across balancing dampers.

Room sound characteristics vary depending on unit selection, air system design, and equipment manufacturer. Select units by considering the unit manufacturer’s sound power ratings, desired maximum room noise level, and the room’s acoustical characteristics. Limits of sound power level can then be specified to obtain acceptable acoustical performance. See Chapter 8 in the 2017 ASHRAE Handbook—Fundamentals.

13. PERFORMANCE UNDER VARYING LOAD

Under peak load conditions, the psychrometrics of induction units, chilled beams, unit ventilators, and fan-coil unit systems are essentially identical for two- and four-pipe systems. Primary air mixes with secondary air conditioned by the room coil in an induction unit before delivery to a room. Mixing also occurs in a fan-coil unit with a direct-connected primary-air supply. If primary air is supplied to the space separately, as in fan-coil systems with independent primary-air supplies, the same effect occurs in the space.

During cooling, the primary-air system provides part of the sensible capacity and all of the dehumidification. The rest of the sensible capacity is accomplished by the cooling effect of secondary water circulating through the in-room terminal unit cooling coils. In winter, when primary air is provided directly into the in-room terminal unit, it can be provided at a low temperature and humidified if necessary. This may allow cooling of internal spaces solely by the primary air, if quantities are sufficient to meet the full cooling requirements. Room heating where needed is then supplied by the secondary-water system circulating through the in-room terminal unit coils.

If the economizer cycle is used, cooling energy can be reduced when the moisture level of the outdoor air allows. For systems where primary air does not enter at the terminal unit, the primary air should enter the room at a temperature approximately neutral with the desired room condition and a relative humidity level that enhances room conditions. In buildings where cooling is required during heating conditions, care must be taken to avoid drafts caused by providing primary air at too low a temperature.

If interior spaces require cooling, a four-pipe system should be considered to allow cooling of those areas while heating exterior perimeter zones. During fall and spring months, the primary-air temperature may be reduced slightly to provide the limited amount of cooling needed for east and west exposures with low internal heat gains, because solar heat gain is typically reduced during these seasons. In the northern hemisphere, the north exposure is not a significant factor because solar gain is very low; for south, southeast, and southwest exposures, the peak solar heat gain occurs in winter, coincident with a lower outdoor temperature (Figure 4). Reducing the primary-air temperature may not be a viable alternative where primary air is supplied directly to the space, because this air could overcool spaces where solar heat gain or internal heat gain is low.

In buildings with large areas of glass, heat transmitted from indoors to the outdoors, coupled with the normal supply of cool primary air, does not balance internal heat and solar gains until an outdoor temperature well below freezing is reached. Double-glazed windows with clear or heat-absorbing glass aggravate this condition, because this type of glass increases the heating effect of the radiant energy that enters during the winter by reducing reverse transmission. Therefore, cooling must be available at lower outdoor temperatures. In buildings with very high internal heat gains from lighting or equipment, the need for cooling from the room coil, as well as from the primary air, can extend well into winter. In any case, the changeover temperature at which the cooling capacity of the secondary-water system is no longer required for a given space is an important calculation. All these factors should be considered when determining the proper changeover temperature.

Solar Radiation Variations with Seasons

Figure 4. Solar Radiation Variations with Seasons


14. CHANGEOVER TEMPERATURE

For all systems using a primary-air system for outdoor air, there is an outdoor temperature (balance temperature) at which secondary cooling is no longer required. The system can cool by using outdoor air at lower temperatures. For all-air systems operating with up to 100% outdoor air, mechanical cooling is seldom required at outdoor temperatures below 55°F, unless the dew point of the outdoor air equals or exceeds the desired indoor dew point. An important characteristic of in-room terminal unit systems, however, is that secondary-water cooling may still be needed, even when the outdoor temperature is considerably less than 50°F. This cooling may be provided by the mechanical refrigeration unit or by a thermal economizer cycle. Full-flow circulation of primary air through the cooling coil below 50°F often provides all the necessary cooling while preventing coil freeze-up and reducing the preheat requirement. Alternatively, secondary-water-to-condenser-water heat exchangers function well.

The outdoor temperature at which the heat gain to every space can be satisfied by the combination of cold primary air and the transmission loss is called the changeover temperature. Below this temperature, cooling is not required.

The following empirical equation approximates the changeover temperature at sea level. It should be fine-tuned after system installation (Carrier 1965):

(1)

where

tco

=

temperature of changeover point, °F

tr

=

room temperature at time of changeover, normally 72°F

tp

=

primary-air temperature at unit after system is changed over, normally 56°F

Qp

=

primary-air quantity, cfm

qis

=

internal sensible heat gain, Btu/h

qes

=

external sensible heat gain, Btu/h

Δqtd

=

heat transmission per degree of temperature difference between room and outdoor air

In two-pipe changeover systems, the entire system is usually changed from winter to summer operation at the same time, so the room with the lowest changeover point should be identified. In northern latitudes, this room usually has a south, southeast, or southwest exposure because the solar heat gains on these exposures reach their maximum during winter.

If the calculated changeover temperature is below approximately 48°F, an economizer cycle should operate to allow the refrigeration plant to shut down.

Although factors controlling the changeover temperature of in-room terminal systems are understood by the design engineer, the basic principles may not be readily apparent to system operators. Therefore, it is important that the concept and calculated changeover temperature are clearly explained in operating instructions given before operating the system. Some increase from the calculated changeover temperature is normal in actual operation. Also, a range or band of changeover temperatures, rather than a single value, is necessary to preclude frequent change in seasonal cycles and to grant some flexibility in operation. The difficulties associated with operator understanding and the need to perform changeover several times a day in many areas have severely limited the acceptability of the two-pipe changeover system.

15. TWO-PIPE SYSTEMS WITH CENTRAL VENTILATION

Two-pipe systems for in-room terminal systems derive their name from the water-distribution circuit, which consists of one supply and one return pipe. Each unit or conditioned space is supplied with secondary water from this distribution system and with conditioned primary air from a central apparatus. The system design and control of primary-air and secondary-water temperatures must be such that all rooms on the same system (or zone, if applicable) can be satisfied during both heating and cooling seasons. The heating or cooling capacity of any unit at a particular time is the sum of its primary-air output plus its secondary-water output.

The secondary-water coil (cooling-heating) in each space is controlled by a space thermostat and can vary from 0 to 100% of coil capacity, as required to maintain space temperature. The secondary water is cold in summer and intermediate seasons and warm in winter. All rooms on the same secondary-water zone must operate satisfactorily with the same water temperature.

Figure 5 shows the capacity ranges available from a typical two-pipe system. On a hot summer day, loads from about 25 to 100% of the design space cooling capacity can be satisfied. On a 50°F intermediate-season day, the unit can satisfy a heating requirement by closing off the secondary-water coil and using only the output of warm primary air. A lesser heating or net cooling requirement is satisfied by the cold secondary-water coil output, which offsets the warm primary air to obtain cooling. In winter, the unit can provide a small amount of cooling by closing the secondary coil and using only the cold primary air. Smaller cooling loads and all heating requirements are satisfied by using warm secondary water.

 Critical Design Elements

The most critical design elements of a two-pipe system are the calculation of primary-air quantities and the final adjustment of the primary-air temperature reset schedule. All rooms require a minimum amount of heat and latent capacity from the primary-air supply during the intermediate season. Using the ratio of primary air to transmission per degree (A/T ratio) to maintain a constant relationship between the primary-air quantity and the heating requirements of each space fulfills this need. The A/T ratio determines the primary-air temperature and changeover point, and is fundamental to proper design and operation of a two-pipe system.

Capacity Ranges of In-Room Terminal Operating on Two-Pipe System

Figure 5. Capacity Ranges of In-Room Terminal Operating on Two-Pipe System


 Transmission per Degree.
 The relative heating requirement of every space is determined by calculating the transmission heat flow per degree temperature difference between the space temperature and the outdoor temperature (assuming steady-state heat transfer). This is the sum of the (1) glass heat transfer coefficient times the glass areas, (2) wall heat transfer coefficient times the wall area, and (3) roof heat transfer coefficient times the roof area.
 Air-to-Transmission (A/T) Ratio.
 The A/T ratio is the ratio of the primary airflow to a given space divided by the transmission per degree of that space: A/T ratio = Primary air/Transmission per degree.

Spaces on a common primary-air zone must have approximately the same A/T ratios. The design base A/T ratio establishes the primary-air reheat schedule during intermediate seasons. Spaces with A/T ratios higher than the design base A/T ratio tend to be overcooled during light cooling loads at an outdoor temperature in the 70 to 90°F range, whereas spaces with an A/T ratio lower than design lack sufficient heat during the 40 to 60°F outdoor temperature range when primary air is warm for heating and secondary water is cold for cooling.

The minimum primary-air quantity that satisfies the requirements for ventilation, dehumidification, and both summer and winter cooling is used to calculate the minimum A/T ratio for each space. If the system operates with primary-air heating during cold weather, the heating capacity can also be the primary-air quantity determinant for two-pipe systems.

The design base A/T ratio is the highest A/T ratio obtained, and the primary airflow to each space is increased as required to obtain a uniform A/T ratio in all spaces. An alternative approach is to locate the space with the highest A/T ratio requirement by inspection, establish the design base A/T ratio, and obtain the primary airflow for all other spaces by multiplying this A/T ratio by the transmission per degree of all other spaces.

For each A/T ratio, there is a specific relationship between outdoor air temperature and temperature of the primary air that maintains the room at 72°F or more during conditions of minimum room cooling load. Figure 6 illustrates this variation based on an assumed minimum room load equivalent to 10°F times the transmission per degree. A primary-air temperature over 122°F at the unit is seldom used. The reheat schedule should be adjusted for hospital rooms or other applications where a higher minimum room temperature is desired, or where a space has no minimum cooling load.

Primary-Air Temperature Versus Outdoor Air Temperature

Figure 6. Primary-Air Temperature Versus Outdoor Air Temperature


Deviation from the A/T ratio is sometimes permissible. A minimum A/T ratio equal to 0.7 of the maximum A/T is suitable, if the building is of massive construction with considerable heat storage effect (Carrier 1965). The heating performance when using warm primary air becomes less satisfactory than that for systems with a uniform A/T ratio. Therefore, systems designed for A/T ratio deviation should be suitable for changeover to warm secondary water for heating whenever the outdoor temperature falls below 40°F. A/T ratios should be more closely maintained on buildings with large glass areas or with curtain wall construction, or on systems with low changeover temperature.

 Changeover Temperature Considerations

Transition from summer operations to intermediate-season operation is done by gradually raising the primary-air temperature as the outdoor temperature falls, to keep rooms with small cooling loads from becoming too cold. The secondary water remains cold during both summer and intermediate seasons. Figure 7 illustrates the psychrometrics of summer operation near the changeover temperature. As the outdoor temperature drops further, the changeover temperature is reached. The secondary-water system can then be changed over to provide hot water for heating.

If the primary airflow is increased to some spaces to elevate the changeover temperature, the A/T ratio for the reheat zone is affected. Adjustments in primary-air quantities to other spaces on that zone will probably be necessary to establish a reasonably uniform ratio.

System changeover can take several hours and usually temporarily upsets room temperatures. Good design, therefore, includes provision for operating the system with either hot or cold secondary water over a range of 15 to 20°F below the changeover point. This range makes it possible to operate with warm air and cold secondary water when the outdoor temperature rises above the daytime changeover temperature. Changeover to hot water is limited to times of extreme or protracted cold weather.

Psychrometric Chart, Two-Pipe System, Off-Season Cooling

Figure 7. Psychrometric Chart, Two-Pipe System, Off-Season Cooling


Optional hot- or cold-water operation below the changeover point is provided by increasing the primary-air reheater capacity to provide adequate heat at a colder outdoor temperature. Figure 8 shows temperature variation for a system operating with changeover, indicating the relative temperature of the primary air and secondary water throughout the year and the changeover temperature range. The solid arrows show the temperature variation when changing over from the summer to the winter cycle. The open arrows show the variation when going from the winter to the summer cycle.

 Nonchangeover Design

Consider using nonchangeover systems to simplify operation for buildings with mild winter climates, or for south exposure zones of buildings with a large winter solar load. A nonchangeover system operates on an intermediate-season cycle throughout the heating season, with cold secondary water to the terminal unit coils and with warm primary air satisfying all the heating requirements. Typical temperature variation is shown in Figure 9.

Spaces may be heated during unoccupied hours by operating the primary-air system with 100% return air. This feature is necessary because nonchangeover design does not usually include the ability to heat the secondary water. In addition, cold secondary water must be available throughout the winter. Primary-air duct insulation and observance of close A/T ratios for all units are essential for proper heating during cold weather.

 Zoning

A two-pipe system can provide good temperature control most of the time, on all exposures during the heating and cooling seasons. Comfort and operating cost can be improved by zoning in the following ways:

  • Primary air to allow different A/T ratios on different exposures

  • Primary air to allow solar compensation of primary-air temperature

  • Both air and water to allow a different changeover temperature for different exposures

Typical Changeover System Temperature Variation

Figure 8. Typical Changeover System Temperature Variation


Typical Nonchangeover System Variations

Figure 9. Typical Nonchangeover System Variations


All spaces on the same primary-air zone must have the same A/T ratio. The minimum A/T ratios often are different for spaces on different solar exposures, thus requiring the primary-air quantities on some exposures to be increased if they are placed on a common zone with other exposures. The primary-air quantity to units serving spaces with less solar exposure can usually be reduced by using separate primary-air zones with different A/T ratios and reheat schedules. Primary-air quantity should never be reduced below minimum ventilation requirements.

The peak cooling load for the south exposure occurs during fall or winter when outdoor temperatures are lower. If shading patterns from adjacent buildings or obstructions are not present, primary-air zoning by solar exposure can reduce air quantities and unit coil sizes on the south. Units can be selected for peak capacity with cold primary air instead of reheated primary air. Primary-air zoning and solar compensators save operating cost on all solar exposures by reducing primary-air reheat and secondary-water refrigeration penalty.

Separate air and water zoning may save operating cost by allowing spaces with less solar exposure to operate on the winter cycle with warm secondary water at outdoor temperatures as high as 60°F during the heating season. Systems with a common secondary-water zone must operate with cold secondary water to cool heavier solar exposures. Primary airflow can be lower because of separate A/T ratios, resulting in reheat and refrigeration cost savings.

 Room Control

When room temperature rises, the thermostat must increase the output of the cold secondary coil (in summer) or decrease the output of the warm secondary coil (in winter). Changeover from cold to hot water in the unit coils requires changing the action of the room temperature control system. Room control for nonchangeover systems does not require the changeover action, unless it is required to provide gravity heating during shutdown.

 Evaluation

Characteristics of two-pipe in-room terminal unit systems include the following:

  • Usually less expensive to install than four-pipe systems

  • Less capable of handling widely varying loads or providing a widely varying choice of room temperatures than four-pipe systems

  • Present operational and control changeover problems, increasing the need for competent operating personnel

  • More costly to operate than four-pipe systems

 Electric Heat for Two-Pipe Systems

Electric heat can be supplied with a two-pipe in-room terminal unit system by a central electric boiler and terminal coils, or by individual electric-resistance heating coils in the terminal units. One method uses small electric-resistance terminal heaters for intermediate-season heating and a two-pipe changeover chilled-water/hot-water system. The electric terminal heater heats when outdoor temperatures are above 40°F, so cooling can be kept available with chilled water in the chilled-water/hot-water system. System or zone reheating of primary air is greatly reduced or eliminated entirely. When the outdoor temperature falls below this point, the chilled-water/hot-water system is switched to hot water, providing greater heating capacity. Changeover is limited to a few times per season, and simultaneous heating/cooling capacity is available, except in extremely cold weather, when little, if any, cooling is needed. If electric-resistance terminal heaters are used, they should be prevented from operating whenever the secondary-water system is operated with hot water.

Another method is to size electric resistance terminal heaters for the peak winter heating load and operate the chilled-water system as a nonchangeover cooling-only system. This avoids the operating problem of chilled-water/hot-water system changeover. In fact, this method functions like a four-pipe system, and, in areas where the electric utility establishes a summer demand charge and has a low unit energy cost for high winter consumption, it may have a lower life-cycle cost than hydronic heating with fossil fuel. A variation, especially appropriate for well-insulated office buildings with induction units where cooling is needed in perimeter offices for almost all occupied hours because of internal heat gain, is to use electric heaters in the terminal unit during occupied hours and to provide heating during unoccupied hours by raising primary-air temperature on an outdoor reset schedule.

16. FOUR-PIPE SYSTEMS

Four-pipe systems have a chilled-water supply, chilled-water return, hot-water supply, and hot-water return. The terminal unit usually has two independent secondary-water coils: one served by hot water, the other by cold water. During peak cooling and heating, the four-pipe system performs in a manner similar to the two-pipe system, with essentially the same operating characteristics. Between seasons, any unit can be operated at any level from maximum cooling to maximum heating, if both cold and warm water are being circulated, or between these extremes without regard to other units’ operation.

In-room terminal units are selected by their peak capacity. The A/T ratio does not apply to four-pipe systems. There is no need to increase primary-air quantities on units with low solar exposure beyond the amount needed for ventilation and to satisfy cooling loads. The available net cooling is not reduced by heating the primary air. The changeover point is still important, though, because cooling spaces on the sunny side of the building may still require secondary-water cooling to supplement the primary air at low outdoor temperatures.

 Zoning

Zoning primary-air or secondary-water systems is not required with four-pipe systems. All terminal units can heat or cool at all times, as long as both hot and cold secondary pumps are operated and sources of heating and cooling are available.

 Room Control

The four-pipe terminal usually has two completely separated secondary-water coils: one receiving hot water and the other receiving cold water. The coils are operated in sequence by the same thermostat; they are never operated simultaneously. The unit receives either hot or cold water in varying amounts, or else no flow is present, as shown in Figure 10A. Adjustable, dead-band thermostats further reduce operating cost.

Figure 10B illustrates another unit and control configuration. A single secondary-water coil at the unit and three-way valves located at the inlet and outlet admit water from either the hot- or cold-water supply, as required, and divert it to the appropriate return pipe. This arrangement requires a special three-way modulating valve, originally developed for one form of the three-pipe system. It controls the hot or cold water selectively and proportionally, but does not mix the streams. The valve at the coil outlet is a two-position valve open to either the hot or cold water return, as required.

Fan-Coil Unit Control

Figure 10. Fan-Coil Unit Control


Overall, the two-coil arrangement provides a superior four-pipe system. Operation of the induction and fan-coil unit controls is the same year-round.

 Evaluation

Compared to the two-pipe system, the four-pipe air-and-water system has the following characteristics:

  • More flexible and adaptable to widely differing loads, responding quickly to load changes

  • Simpler to operate

  • Operates without the summer-winter changeover and primary-air reheat schedule

  • Efficiency is greater and operating cost is lower, though initial cost is generally higher

  • Can be designed with no interconnection of hot- and cold-water secondary circuits, and the secondary system can be completely independent of the primary-water piping

17. AUTOMATIC CONTROLS AND BUILDING MANAGEMENT SYSTEMS

Chapter 47 of the 2019 ASHRAE Handbook—HVAC Applications and Chapter 7 of the 2017 ASHRAE Handbook—Fundamentals discuss automatic controls. The information and concepts discussed there apply to in-room terminal system equipment and systems, as well.

The designer should discuss the complexity, technical expertise, and local resources with the facility’s owner/operator before specifying a overly complex or sophisticated control system, because many facilities using in-room terminal units have limited maintenance staff.

18. MAINTENANCE MANAGEMENT SYSTEMS AND BUILDING SYSTEM COMMISSIONING

Chapter 1 discusses both of these topics. In-room terminal systems, like every other system, benefit from consideration and implementation of these practices.

REFERENCES

AHRI. 2008. Performance rating of room fan-coils. ANSI/AHRI Standard 440-2008. Air-Conditioning, Heating, and Refrigeration Institute, Arlington, VA.

AHRI. 1998. Unit ventilators. Standard 840-1998. Air-Conditioning, Heating, and Refrigeration Institute, Arlington, VA.

AIA. 2001. Guidelines for design and construction of hospital and health care facilities. American Institute of Architects, Washington, D.C.

ASHRAE. 2013. Safety standards for refrigeration systems. ANSI/ASHRAE Standard 15-2013.

ASHRAE. 2013. Ventilation for acceptable indoor air quality. ANSI/ASHRAE Standard 62.1-2013.

ASHRAE. 2002. Method of testing for rating fan coil conditioners. ANSI/ASHRAE Standard 79-2002.

Carrier Air Conditioning Company. 1965. Handbook of air conditioning system design. McGraw-Hill, New York.

BIBLIOGRAPHY

ASHRAE. 2014. Methods of testing for rating room air conditioners and packaged terminal air conditioners. ANSI/ASHRAE Standard 16-1983 (RA 2014).

ASHRAE. 2013. Thermal environmental conditions for human occupancy. ANSI/ASHRAE Standard 55-2013.

ASHRAE. 2014. Methods of testing for rating room air conditioners and packaged terminal air conditioner heating capacity. ANSI/ASHRAE Standard 58-1986 (RA 2014).

ASHRAE. 2013. Ventilation for acceptable indoor air quality in low-rise residential buildings. ANSI/ASHRAE Standard 62.2-2013.

ASHRAE. 2011. Method of testing for rating the performance of air outlets and air inlets. ANSI/ASHRAE Standard 70-2006 (RA 2011).

ASHRAE. 2013. Energy standard for buildings except low-rise residential buildings. ANSI/ASHRAE Standard 90.1-2013.

ASHRAE. 2007. Energy standard of low-rise residential buildings. ANSI/ASHRAE Standard 90.2-2007.

ASHRAE. 2015. Energy conservation in existing buildings. ANSI/ASHRAE Standard 100-2015.

ASHRAE. 2013. Methods of testing for room air diffusion. ANSI/ASHRAE Standard 113-2013.

ASHRAE. 2012. Methods of testing for rating computer and data processing room unitary air conditioners. ANSI/ASHRAE Standard 127-2012.

ASHRAE. 2008. Methods of testing for rating ducted air terminal units. ANSI/ASHRAE Standard 130-2008.

ASHRAE. 2012. BACnet®: A data communication protocol for building automation and control networks. ANSI/ASHRAE Standard 135-2012.

ASHRAE. 2013. Methods of testing for radiant ceiling panels for sensible heating and cooling. ANSI/ASHRAE Standard 138-2013.

ASHRAE. 2013. Climate data for building design standards. ANSI/ASHRAE Standard 169-2013.

ASHRAE. 2012. Standard practice for inspection and maintenance of commercial building HVAC systems. ANSI/ASHRAE/ACCA Standard 180-2012.

ASHRAE. 2014. Standard for the design of high-performance green buildings. ANSI/ASHRAE/USGCB/IES Standard 189.1-2014.

ASHRAE. 2013. Method of test for rating air terminal unit controls. ANSI/ASHRAE Standard 195-2013.

ASHRAE. 2013. Commissioning process for buildings and systems. ANSI/ASHRAE/IES Standard 202-2013.

ASHRAE. 2013. The commissioning process. Guideline 0-2013.

ASHRAE. 2009. Guideline for the risk management of public health and safety in buildings. Guideline 29-2009.



The preparation of this chapter is assigned to TC 9.1, Large Building Air-Conditioning Systems.